What is the expected level of details on calls in the bid?
Bidders are not asked to elaborate call details in their bid. The Bid Form requires an overall plan for calls with the expected timing (by quarter and year, e.g. Q2 2026), under which output(s) the call falls, grant size, etc. This plan from the Bid Form is intended to provide a basis for the draft Programme Implementation Agreement, and depending on the plan there can be some initial calls launched early following signature of the Programme Implementation Agreement. Kindly note that there is also flexibility for reallocations between calls later on. Please see the separate question and answer on reallocations, here.